On the ongoing TANAP project, RAS is currently working on two assigned spreads in parallel. On one spread air cleaning and gauging is terminated and the first test section is due to filling next week whereas on the other spread two sections have been already successfully hydro tested. Not only are these the first tested sections for the entire Trans-Anatolian Natural Gas Pipeline project but also the very first 56" pipeline sections to be tested in Turkey.